COnstructive COst MOdel (Boehm, 1981): an algorithmic cost-estimation model fitted from real project data. Basic COCOMO estimates effort and schedule from KLOC alone; intermediate/detailed variants layer in cost drivers.
Basic effort: $E = a \cdot (\text{KLOC})^b$ person-months
Basic schedule: $D = c \cdot E^d$ months
Organic (small, familiar): $a=2.4,\ b=1.05,\ c=2.5,\ d=0.38$
Semi-detached (medium): $a=3.0,\ b=1.12,\ c=2.5,\ d=0.35$
Embedded (large, strict constraints): $a=3.6,\ b=1.20,\ c=2.5,\ d=0.32$